2023
Investor: ROSICE PARK a.s. | Location of Construction: Rosice nad Labem | Financial Volume: 45 208 000 EUR | Date of Implementation: 01/2022 – 06/2023 | About the Project: New construction of two production-assembly and storage halls with a total floor area of 49.2 thousand m2, containing administrative built-in units
2023
Investor: Milotice Winery | Location of Construction: Milotice | Financial Volume: 1 683 000 EUR | Date of Implementation: 5/2022 – 5/2023 | About the Project: General contractor
2018
Investor: POWERBRIDGE spol. s r.o. | Location of Construction: Popůvky | Financial Volume: 1 611 100 EUR | Date of Implementation: 08/2017 – 05/2018 | About the Project: Construction of a new company headquarters
2020
Investor: LETIŠTĚ BRNO a.s. | Location of Construction: Brno–Tuřany | Financial Volume: 15 952 000 EUR | Date of Implementation: 12/2018 – 02/2020 | About the Project: Construction of a new warehouse hall with dimensions 422 x 76 m, the building is divided into 7 units, including administrative annexes, maintenance, and technical built-in units